Dear Neighbour
Please see below activities relating to the Sydenham Hill Estate Project which are due to take place from Monday 23 January 2023.
Monday 23 January – Friday 27 January
Works will include:
Installing timber hoarding around Mais House, including the pedestrian walkway
Installing Heras (metal mesh) fencing around the tree protection areas in the Mais House part of the site
Installing TBS (temporary building electrical supply pads that electrical supply will sit on)
Soft strip of Mais House, starting 23/01. This work will involve the stripping out of the any interior fixtures, internal ceilings, temporary and removable structures that aren’t integral to the building
Installation of scaffold to three locations on Mais house to aid in the bat relocation works that will occur at a future date
Saturday 28 January – Sunday 29 January
No works.
Possible disruption
The walkway between Lammas Green and Mais House will be partially blocked during the installation of the hoarding along this path. There will also be a vehicle parked off road next to the walkway. This will take 2-3 days. Pedestrian access will be maintained throughout the installation of the hoarding in this area
Deliveries
Skip and trailer for soft strip removal via the main gate.
Daily delivery of hoarding materials by rigid transport
Non-Lovell Works
Sitex shutter removal from Mais House (due for completion 20/1)
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 9:00 to 13:00
For site emergencies, please contact:
Garfield Williams, Lovell
T: 07721 628436 or 020 8731 3800 (0800 030 4690 out of hours)