Sydenham Hill Estate Weekly Works Update: w/c Monday 10 November 2025

Dear Neighbour,

Please find below the activities that are scheduled to take place for the next week in connection with Sydenham Hill Estate Redevelopment Project.


Monday 10 - Friday 14 November; Saturday 15 November (08.00 – 13.00)


Bean Tree Court

  • Handover

Landscaping/Externals

  • Landscaping works continue – turf, paving, planting

Otto Close Houses

  • Internal decorating , kitchens installation, flooring

  • Paving to rear gardens

Otto Close Pitch

  • Concrete pad for gate


Deliveries

  • Several deliveries (landscaping and drylining materials). These will all be offloaded quickly and the vehicles can be moved if required.

Note/Future works

  • Bus stop relocation back to original location is underway c/o TFL’s contractors

  • Weekend works (outside regular hours): On Saturday 8 November afternoon/Sunday 9 November the following quiet works will take place: Internal cleaning at Bean Tree Court and Soft Landscaping. We have reminded contractors that any noisy works must stop at 1pm on Saturday and not take place on Sunday.

    There will be no Saturday afternoon/Sunday works the following weekend (15/16 November).


If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best Wishes,

The Sydenham Hill Project Team

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

 For site emergencies, please contact:

Andrew Neary            07436 049 480

Hannah Morgan          07769 306 933

Tony Clissold              07890 036 501

Laury Jancauskas     07502 600 834