Dear Neighbour,
Please find below the activities that are scheduled to take place for the next week in connection with Sydenham Hill Estate Redevelopment Project.
Monday 10 - Friday 14 November; Saturday 15 November (08.00 – 13.00)
Bean Tree Court
Handover
Landscaping/Externals
Landscaping works continue – turf, paving, planting
Otto Close Houses
Internal decorating , kitchens installation, flooring
Paving to rear gardens
Otto Close Pitch
Concrete pad for gate
Deliveries
Several deliveries (landscaping and drylining materials). These will all be offloaded quickly and the vehicles can be moved if required.
Note/Future works
Bus stop relocation back to original location is underway c/o TFL’s contractors
Weekend works (outside regular hours): On Saturday 8 November afternoon/Sunday 9 November the following quiet works will take place: Internal cleaning at Bean Tree Court and Soft Landscaping. We have reminded contractors that any noisy works must stop at 1pm on Saturday and not take place on Sunday.
There will be no Saturday afternoon/Sunday works the following weekend (15/16 November).
If you have any queries, please contact us on info@sydenhamhillproject.com
Best Wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact:
Andrew Neary 07436 049 480
Hannah Morgan 07769 306 933
Tony Clissold 07890 036 501
Laury Jancauskas 07502 600 834