Please find below the activities that are scheduled to take place for the next week in connection with Sydenham Hill Estate Redevelopment Project.


Monday 17 - Friday 21 November; Saturday 22 November (08.00 – 13.00)


Bean Tree Court

  • Snagging & cleaning paving

Landscaping/Externals

  • Landscaping works continue – turf, paving, planting – including to the rear gardens of Otto Close (see previous email)

  • The pathway between Lammas Green and Otto Close remains closed – the brickwork is complete; handrails to be installed by new steps

Otto Close Houses

  • Internals including decorating, doors & frames, switches & lighting, tiling & flooring

  • Paving to rear gardens

  • Front garden footing and walls

Otto Close Pitch

  • Clear out of materials


Deliveries

  • Several deliveries (landscaping, joinery and flooring materials). These will all be offloaded quickly and the vehicles can be moved if required.


If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best Wishes,

The Sydenham Hill Project Team

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

 For site emergencies, please contact:

Andrew Neary            07436 049 480

Tony Clissold              07890 036 501

Laury Jancauskas     07502 600 834

Click to download as PDF