Dear Neighbour,
Please find below the activities that are scheduled to take place for the next week in connection with Sydenham Hill Estate Redevelopment Project.
Monday 17 - Friday 21 November; Saturday 22 November (08.00 – 13.00)
Bean Tree Court
Snagging & cleaning paving
Landscaping/Externals
Landscaping works continue – turf, paving, planting – including to the rear gardens of Otto Close (see previous email)
The pathway between Lammas Green and Otto Close remains closed – the brickwork is complete; handrails to be installed by new steps
Otto Close Houses
Internals including decorating, doors & frames, switches & lighting, tiling & flooring
Paving to rear gardens
Front garden footing and walls
Otto Close Pitch
Clear out of materials
Deliveries
Several deliveries (landscaping, joinery and flooring materials). These will all be offloaded quickly and the vehicles can be moved if required.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best Wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact:
Andrew Neary 07436 049 480
Tony Clissold 07890 036 501
Laury Jancauskas 07502 600 834