Dear Neighbour,
Please find below the activities that are scheduled to take place for the next week in connection with Sydenham Hill Estate Redevelopment Project.
Monday 27 - Friday 31 October; Saturday 1 November (08.00 – 13.00)
Bean Tree Court
Closing out internal snags
Sparkle cleans of apartments
Landscaping/Externals
Landscaping works continue – topsoil and paving - see note and plan below
Brickwork on pathway between Lammas Green & Otto Close - the pathway remains closed
Otto Close Houses
Internal decorating , mechanical & electrical 2nd fix
Paving to rear gardens
Otto Close Pitch
Concrete pad for gate
Deliveries
Several deliveries (landscaping and drylining materials). These will all be offloaded quickly and the vehicles can be moved if required.
Note/Future works
Bus stop relocation (by TFL contractors): We are still awaiting the start date from TFL which will not be before w/c 3 November.
Landscaping works: From 27 October, landscape remediation works will begin in the main grassed area to clean up and make the ground safe before landscaping. During this time, the internal paths will be closed - see photo/plan below.
Weekend works: Please note that the works listed above will take place on Saturday until 1pm.
On Saturday afternoons and Sundays, the following quiet works will take place: Internal cleaning at Bean Tree Court and Soft Landscaping.
We would like to apologise for the noisy works which took place last Sunday. We have reminded contractors that any cutting must stop at 1pm on Saturday and not take place on Sunday.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best Wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact:
Andrew Neary 07436 049 480
Hannah Morgan 07769 306 933
Tony Clissold 07890 036 501
Dion King 07901 737 269
Laury Jancauskas 07502 600 834
Security 07759 833 036