Please find below the activities that are scheduled to take place for the next week in connection with Sydenham Hill Estate Redevelopment Project.
Monday 20 - Friday 24 October; Saturday 25 October (08.00 – 13.00)
Bean Tree Court
Closing out internal snags
Installation of car chargers
Landscaping/Externals
Landscaping works continue – topsoil and paving
Brickwork on pathway between Lammas Green & Otto Close
Otto Close Houses
Internal decorating
Paving to rear gardens
Slabs for bin stores at front of houses
Otto Close Pitch
Concrete pad for gate
Note
Pathway resurfacing works above the steps in Lammas Green are ongoing and this route between Lammas Green and Otto Close will be closed. The path is expected to be closed for 6 weeks whilst the works take place.
Weekend works: Landscaping will take place on Saturdays and Sundays until mid-November (provisional hours 8am–4pm at the latest). We apologise for any inconvenience this may cause.
Some internal works at Bean Tree Court will also take place on Saturdays and Sundays outside of the general working hours: These will be internal quiet works only (primarily cleaning).
Bus stop relocation (by TFL contractors): These works did not take place last week as expected. We have chased TFL for the start date and send out a notification when we receive confirmation.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best Wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact:
Andrew Neary 07436 049 480
Hannah Morgan 07769 306 933
Tony Clissold 07890 036 501
Dion King 07901 737 269
Laury Jancauskas 07502 600 834
Security 07759 833 036