Sydenham Hill Estate Weekly Works Update: w/c Monday 20 October 2025

Dear Neighbour,

Please find below the activities that are scheduled to take place for the next week in connection with Sydenham Hill Estate Redevelopment Project.

Monday 20 - Friday 24 October; Saturday 25 October (08.00 – 13.00)

Bean Tree Court

  • Closing out internal snags

  • Installation of car chargers

Landscaping/Externals

  • Landscaping works continue – topsoil and paving

  • Brickwork on pathway between Lammas Green & Otto Close

Otto Close Houses

  • Internal decorating

  • Paving to rear gardens

  • Slabs for bin stores at front of houses

Otto Close Pitch

  • Concrete pad for gate

Note

  • Pathway resurfacing works above the steps in Lammas Green are ongoing and this route between Lammas Green and Otto Close will be closed. The path is expected to be closed for 6 weeks whilst the works take place.

  • Weekend works: Landscaping will take place on Saturdays and Sundays until mid-November (provisional hours 8am–4pm at the latest). We apologise for any inconvenience this may cause.

  • Some internal works at Bean Tree Court will also take place on Saturdays and Sundays outside of the general working hours: These will be internal quiet works only (primarily cleaning).

  • Bus stop relocation (by TFL contractors): These works did not take place last week as expected. We have chased TFL for the start date and send out a notification when we receive confirmation.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best Wishes,

The Sydenham Hill Project Team

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

 For site emergencies, please contact:

Andrew Neary            07436 049 480

Hannah Morgan          07769 306 933

Tony Clissold              07890 036 501

Dion King                     07901 737 269

Laury Jancauskas     07502 600 834

Security                       07759 833 036

Click to download as PDF