Dear Neighbour,
Please find below the activities that are scheduled to take place for the next week in connection with Sydenham Hill Estate Redevelopment Project.
Monday 13 - Friday 17 October; Saturday 18 October (08.00 – 13.00)
Bean Tree Court
Practical completion of the building
Final snagging & cleaning internally
Landscaping/Externals
Landscaping works continue - top soil & paving
Installation of car chargers
Hoarding removal & brickwork - pathway between Lammas Green & Otto Close*
Otto Close Houses
Roof insulation, internal plastering & plasterboard
Works to rear gardens continue
Excavation for water & electrical connection at entrance of Otto Close - vehicle access will be maintained
Otto Close Pitch
Concrete pad for gate
Note
The pathway from Sydenham Hill to Otto Close has reopened.
Pathway resurfacing works above the steps in Lammas Green have started and this route between Lammas Green and Otto Close will be closed. The path is expected to be closed for 6 weeks whilst the works take place.
Some internal works at Bean Tree Court will take place on Saturday and Sunday outside of the general working hours: 8am-4pm (at the latest). These will be internal quiet works only (primarily cleaning).
Bus stop relocation (by TFL contractors): These works did not take place this week as expected. We have chased TFL for the start date and send out a notification when we receive confirmation.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best Wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact:
Andrew Neary 07436 049 480
Hannah Morgan 07769 306 933
Tony Clissold 07890 036 501
Dion King 07901 737 269
Laury Jancauskas 07502 600 834
Security 07759 833 036