Please find below the activities that are scheduled to take place for the next week in connection with Sydenham Hill Estate Redevelopment Project.

Monday 6 - Friday 10 October; Saturday 11 October (08.00 – 13.00)

Bean Tree Court, Block A

  • Final cleaning of apartments & common areas

Block B

  • Decoration snagging & flooring to corridors & stairwells

  • Snagging of apartments

  • Commissioning of mechanical & electrical systems

Block C

  • Snagging & final cleaning of apartments & corridors

Landscaping/Externals

  • Landscaping works continue - top soil & paving

  • Landscaping to path from Sydenham Hill completes*

  • Installation of ducts for car chargers

  • Snagging to roof areas from scaffold towers

  • Hoarding removal & brickwork - pathway between Lammas Green & Otto Close*

Otto Close Houses

  • Roof insulation, internal plastering & plasterboard

  • Works to rear gardens

  • Excavation for water connection at entrance of Otto Close - vehicle access will be maintained

  • Excavation to front of plots for electrical connection

Otto Close Pitch

  • No works planned

Note

  • Pathway closures: The works to the alleyway from Sydenham Hill to Otto Close are due to complete on Monday 6 October and this route will then reopen.

  • Once this path has reopened, pathway resurfacing works above the zigzag in Lammas Green will start and this route between Lammas Green and Otto Close will be closed. The path is expected to be closed for 6 weeks whilst works to the path and steps take place (see attached poster which shows the path closure and alternate route).

  • Bus stop relocation: We have been advised by TFL that works to relocate the bus stop back to in front of Bean Tree Court will take place in w/c 6 October. We haven’t received confirmation of a start date and any potential road/pavement closures, but will send out notification when we receive it.

  • Some internal works at Bean Tree Court will take place on Saturday and Sunday outside of the general working hours: 8am-4pm (at the latest). These will be internal quiet works only (decoration and plastering to walls).

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best Wishes,

The Sydenham Hill Project Team

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

 For site emergencies, please contact:

Andrew Neary            07436 049 480

Hannah Morgan          07769 306 933

Tony Clissold              07890 036 501

Dion King                     07901 737 269

Laury Jancauskas     07502 600 834

Security                       07759 833 036