Sydenham Hill Estate Weekly Works Update: w/c Monday 29 September 2025

Dear Neighbour,

Please find below the activities that are scheduled to take place for the next week in connection with Sydenham Hill Estate Redevelopment Project.

Monday 29 September - Friday 3 October; Saturday 4 October (08.00 – 13.00)

Bean Tree Court, Block A

  • Final snagging & cleaning of apartments & corridors

  • Commissioning of mechanical & electrical systems

Block B

  • Decoration & flooring to corridors & stairwells

  • Snagging of apartments

  • Commissioning of mechanical & electrical systems

Block C

  • Decoration & snagging - apartments & corridors

  • Tiling stairwell walls

  • Painting of cycle store & installation of cycle racks

  • Commissioning of mechanical & electrical systems

Landscaping/Externals

  • Removal of storage containers

  • Installation of main gate

  • Landscaping works to play area and externals of Block C

  • Landscaping to path from Sydenham Hill continues

  • Installation of ducts for car chargers

  • Cherry picker on site to carry out snagging to roof areas

Otto Close Houses

  • Roof insulation, internal plastering & plasterboard

  • Works to rear gardens

  • Excavation for water connection at entrance of Otto Close - vehicle access will be maintained

Otto Close Pitch

  • No works planned

Deliveries

  • There will be a scaffold collection from Otto Close on Tuesday 30 September

Note

  • The footpath from Sydenham Hill to Otto Close is now closed (from Monday 15 September for 2-3 weeks. The diversion route will be via Lammas Green.

  • Pathway resurfacing works in Lammas Green (above zigzag) are anticipated to start in 3 weeks’ time and will mean the pathway through to Otto Close will be closed. These works will not start until works to the alleyway from Sydenham Hill have been completed. We will advise of a start date in future updates.

  • Some internal works at Bean Tree Court will take place on Saturday and Sunday outside of the general working hours: 8am-4pm (at the latest). These will be internal quiet works only (decoration and plastering to walls).

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best Wishes,

The Sydenham Hill Project Team

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

 For site emergencies, please contact:

Andrew Neary            07436 049 480

Hannah Morgan          07769 306 933

Tony Clissold              07890 036 501

Dion King                     07901 737 269

Laury Jancauskas     07502 600 834

Security                       07759 833 036