Sydenham Hill Estate Weekly Works Update: w/c Monday 7 July 2025

Dear Neighbour,

Please find below the activities that are scheduled to take place from the week commencing Monday 7 July 2025 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 7 - Friday 11 July; Saturday 12 July (08.00 – 13.00)

Bean Tree Court, Block A

  • Snagging to all apartments

  • Connection of door entry system

  • Lift commissioning ongoing

  • Tiling to main entrance area walls

  • Landscaping to perimeter

Block B

  • Decoration to various apartments, 2nd -3rd floor

  • Skirting, doors & floors, Ground & 1st floor

  • Kitchens & tiling, 4th - 6th floor

  • Plastering & painting corridors

  • Scaffold strike to perimeter continues

Block C

  • Finals & decorations to various apartments

  • Snagging – 1st floor

  • Bathrooms & kitchens - various apartments

  • Lift commissioning

  • Landscaping to front of entrance

Otto Close

  • Roofs & zinc, external snagging, ventilation installation, scaffold strike - houses 1-4

  • Roof tiling, internal dry-lining - houses 5-11

Pitch

  • Completion of demolition

  • External brickwork and installing padstones

Deliveries

  • No scaffold collection planned

  • There may be a plant (vehicle) collection this week in Otto Close – we will send notification if so.

Note/Future works

  • We are planning to lay the concrete floor planks on the pitch on Monday 14 July – Tuesday 15 July, which will mean some disruption to vehicles in Otto Close on those dates.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best Wishes,

The Sydenham Hill Project Team

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

 For site emergencies, please contact:

Andrew Neary 07436 049 480

Hannah Morgan          07769 306 933

Dion King                     07901 737 269

Laury Jancauskas         07502 600 834