Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 7 July 2025 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 7 - Friday 11 July; Saturday 12 July (08.00 – 13.00)
Bean Tree Court, Block A
Snagging to all apartments
Connection of door entry system
Lift commissioning ongoing
Tiling to main entrance area walls
Landscaping to perimeter
Block B
Decoration to various apartments, 2nd -3rd floor
Skirting, doors & floors, Ground & 1st floor
Kitchens & tiling, 4th - 6th floor
Plastering & painting corridors
Scaffold strike to perimeter continues
Block C
Finals & decorations to various apartments
Snagging – 1st floor
Bathrooms & kitchens - various apartments
Lift commissioning
Landscaping to front of entrance
Otto Close
Roofs & zinc, external snagging, ventilation installation, scaffold strike - houses 1-4
Roof tiling, internal dry-lining - houses 5-11
Pitch
Completion of demolition
External brickwork and installing padstones
Deliveries
No scaffold collection planned
There may be a plant (vehicle) collection this week in Otto Close – we will send notification if so.
Note/Future works
We are planning to lay the concrete floor planks on the pitch on Monday 14 July – Tuesday 15 July, which will mean some disruption to vehicles in Otto Close on those dates.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best Wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact:
Andrew Neary 07436 049 480
Hannah Morgan 07769 306 933
Dion King 07901 737 269
Laury Jancauskas 07502 600 834
Security 07759 833 036