Sydenham Hill Estate Weekly Works Update: w/c Tuesday 26 August 2025

Dear Neighbour,

Please find below the activities that are scheduled to take place for the next week in connection with Sydenham Hill Estate Redevelopment Project.

Tuesday 26 – Friday 29 August: Saturday 30 August (08.00 – 13.00) - No work on Bank holiday Monday.

Bean Tree Court, Block A

  • Sign off & final clean to all apartments

  • Commissioning of mechanical & electrical systems in apartments

  • Corridor & stairwell painting & cleaning

  • Landscaping to Gate 2 area

Block B

  • Decoration & flooring in common areas

  • Floors – 5th floor apartments & corridors

  • Decoration & finals to various apartments

  • Kitchens & bathrooms tiling

  • Paving to perimeter of block

Block C

  • Checking & snagging all apartments

  • Decorations & snagging to corridors

Otto Close Houses

  • Ductwork installation, internal walls, front doors - houses 1-7

  • Zinc to lower level flat roofs, mechanical & electrical first fix, snag rear elevation and strike scaffold - houses 8-11

Otto Close Pitch (updated timeline attached below)

  • Concrete topping & kerbs

  • Concrete & finishing to columns in car park

  • Concrete pump will be positioned in the road on Wednesday 27 August – * see note below

Note/Future works

  • Concrete pumping on pitch: Wednesday 27 August. There will be concrete pump parked across Otto Close blocking access to the end of the Close for around 4 hours. Cars parked above this will be advised to move on Tuesday 26 August. Should there be a need for the emergency services, then arrangements will be made to allow them access.

  • Lovell offices and welfare cabins will be moved Saturday 23 August. This is targeted to complete by 4pm on Saturday although may run into Sunday if there are any delays with the crane and collection vehicles. The welfare is being moved to the area by gate 1 and the move is not expected to cause any disruption to residents. A plan is attached of the existing and new locations and environmental health has been advised of the extended hours.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best Wishes,

The Sydenham Hill Project Team

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

 For site emergencies, please contact:

Andrew Neary            07436 049 480

Hannah Morgan          07769 306 933

Tony Clissold              07890 036 501

Dion King                     07901 737 269

Laury Jancauskas     07502 600 834

Security                       07759 833 036