Sydenham Hill Estate Weekly Works Update: w/c Monday 28 July & w/c Monday 4 August 2025

Dear Neighbour,

Please find below the activities that are scheduled to take place for the next 2 weeks in connection with Sydenham Hill Estate Redevelopment Project.

Monday 28 July - Friday 1 August; Saturday 2 August (08.00 – 13.00) &

Monday 4 – Friday 8 August: Saturday 9 August (08.00 – 13.00)

Bean Tree Court, Block A

  • Sign off & final clean to all apartments

  • Commissioning of mechanical & electrical systems in apartments

  • Corridor & stairwell decoration

  • Lift commissioning and sign off

  • Landscaping to Gate 2 area

Block B

  • Decoration & flooring in common areas

  • Corridors lights & switches

  • Floors – 5th floor apartments & corridors

  • Decoration & finals to various apartments

  • Kitchens & bathrooms tiling

  • Landscaping to undercroft area

  • Tiling floors in lobby area*

Block C

  • Finals & decorations to various apartments

  • Pre-decoration snagging and floors to corridors

  • Snagging – various apartments

  • Lift commissioning & testing

Otto Close Houses

  • External cleaning/snagging, internal walls & pipework, scaffold strike - houses 1-7

  • External cleaning/snagging, mechanical & electrical setting out, internal walls first fix, scaffold strike - houses 5-11

Otto Close Pitch

  • Complete concrete topping

  • Brickwork to new entrance

Deliveries

  • Any scaffold collections will be advised

  • The mobile crane at the pitch was unable to finish on Wednesday 23 July so had to return on Friday 25 July – we apologise for the lack of notice.

Note/Future works

  • Weekend works: We will be working to tile the entrance lobby to block B on Saturday and Sunday, 8am-4pm. These are quiet works and will not affect residents and have been agreed with the Council.

  • Meet the Contractor (tour of new flats). We had asked you to save the date for Tuesday 12 August, however it will be necessary to postpone this until after the summer holidays. We will send out flyers once the new date has been confirmed with information on how to join the event which is likely to take place in early September.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best Wishes,

The Sydenham Hill Project Team

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

 For site emergencies, please contact:

Andrew Neary            07436 049 480

Tony Clissold              07890 036 501

Dion King                     07901 737 269

Laury Jancauskas     07502 600 834

Security                       07759 833 036