Dear Neighbour,
Please find below the activities that are scheduled to take place for the next week in connection with Sydenham Hill Estate Redevelopment Project.
Monday 11 – Friday 15 August: Saturday 16 August (08.00 – 13.00)
Bean Tree Court, Block A
Sign off & final clean to all apartments
Commissioning of mechanical & electrical systems in apartments
Corridor & stairwell decoration & snagging
Landscaping to Gate 2 area
Block B
Decoration & flooring in common areas
Corridors lights & switches
Floors – 4th floor apartments & corridors
Decoration & finals to various apartments
Kitchens & bathrooms tiling
Landscaping to undercroft area
Tiling floors in lobby area*
Block C
Checking & snagging all apartments
Pre-decoration snagging & floors to corridors
Lift testing
Otto Close Houses
Ductwork installation, internal walls - houses 1-7
External cleaning/snagging, mechanical & electrical first fix, timber work to lower roofs, scaffold strike - houses 5-11
Otto Close Pitch
Complete concrete topping
Brickwork to new entrance
Deliveries
No scaffold collections planned for this week
Note/Future works
Weekend works: We will be working to tile the entrance lobby on Saturday and Sunday, 8am-4pm. These are quiet works and will not affect residents and have been agreed with the Council.
Meet the Contractor (tour of new flats). We had asked you to save the date for Tuesday 12 August, however it will be necessary to postpone this until after the summer holidays. We will send out information flyers once the new date has been confirmed.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best Wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00