Sydenham Hill Estate Weekly Works Update: w/c Monday 19 May 2025

Dear Neighbour,

Please find below the activities that are scheduled to take place from the week commencing Monday 19 May 2025 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 19 – Friday 23 May; Saturday 24 May (08.00 – 13.00)

Block A

  • Cable tray install to roof

  • Boarding of staircore door and lift reveal, all floors

  • Live electrical testing, 3rd floor apartments

  • Latex & lino floors, 3rd floor

  • Kitchen & bathroom tiling to remaining apartments on 2nd & 3rd floor

  • Snagging & finals to all apartments ongoing

  • Lift commissioning continues

  • Paving to terraces

Block B

  • Electrical first fix, ground floor

  • Sprinkler installation, ground floor

  • Doors & skirting, 5th floor

  • Plastering & mist coat 6th floor apartments

  • Corridor ceiling grids

  • Tiling to 7th floor roof

  • Scaffold strike to perimeter

Block C

  • Cabling to lower ground floor

  • Pre-decoration snagging, first floor

  • Tiling to bathrooms & kitchens

  • Kitchen installations, various apartments

  • Wall & ceiling closures, 3rd floor

  • Electrical 2nd fix, 3rd floor

  • Final decorations to various apartments

Otto Close

  • Zinc to rear dormas, low level roof work, temporary waterproofing, first fix mechanical & electrical internals - houses 1-4

  • Zinc to rear dormas, roof tiling, internal drylining, bay window protection, houses 5-7

  • Felt & batton to roofs, completing internal staircases, houses 8-11

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best Wishes,

The Sydenham Hill Project Team

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

 For site emergencies, please contact:

Andrew Neary 07436 049 480

Hannah Morgan          07769 306 933

Dion King                     07901 737 269

Laury Jancauskas         07502 600 834

Security 07759 833 036