Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 19 May 2025 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 19 – Friday 23 May; Saturday 24 May (08.00 – 13.00)
Block A
Cable tray install to roof
Boarding of staircore door and lift reveal, all floors
Live electrical testing, 3rd floor apartments
Latex & lino floors, 3rd floor
Kitchen & bathroom tiling to remaining apartments on 2nd & 3rd floor
Snagging & finals to all apartments ongoing
Lift commissioning continues
Paving to terraces
Block B
Electrical first fix, ground floor
Sprinkler installation, ground floor
Doors & skirting, 5th floor
Plastering & mist coat 6th floor apartments
Corridor ceiling grids
Tiling to 7th floor roof
Scaffold strike to perimeter
Block C
Cabling to lower ground floor
Pre-decoration snagging, first floor
Tiling to bathrooms & kitchens
Kitchen installations, various apartments
Wall & ceiling closures, 3rd floor
Electrical 2nd fix, 3rd floor
Final decorations to various apartments
Otto Close
Zinc to rear dormas, low level roof work, temporary waterproofing, first fix mechanical & electrical internals - houses 1-4
Zinc to rear dormas, roof tiling, internal drylining, bay window protection, houses 5-7
Felt & batton to roofs, completing internal staircases, houses 8-11
If you have any queries, please contact us on info@sydenhamhillproject.com
Best Wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00