Please find below the activities that are scheduled to take place from the week commencing Monday 12 May 2025 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 12 – Friday 16 May; Saturday 17 May (08.00 – 13.00)
Block A
Ductwork measure to roof
Boarding of staircore door and lift reveal, all floors
Live electrical testing, 2nd floor apartments
Latex & lino floors, 3rd floor
Kitchen & bathroom tiling to remaining apartments on 2nd & 3rd floor
Snagging & finals to all apartments ongoing
Lift commissioning continues
Landscaping works to perimeter
Block B
Doors & skirting, 4th floor
Plastering & mist coat 5th floor apartments
Electrical 2nd fix to 5th floor
Walls & ceiling closures, 6th floor
Tiling to 7th floor roof
Scaffold strike from 4th floor roof
Block C
Balcony installations, Monday & Tuesday
Final decorations to various apartments
Tiling to bathrooms & kitchens
Kitchen installations, various apartments
Wall & ceiling closures, 2nd & 3rd floor
Electrical 2nd fix, 3rd floor
Otto Close
Roof tiling; windows to front elevation dormas, houses 1-4
Zinc & window installation & roof tiling, houses 5-7
Completing dormas to rear elevation, 1st floor windows, houses 8-11
Installation of temporary footpath
Soft start to ballcourt works – stripping out of internals and Heras fencing to perimeter
If you have any queries, please contact us on info@sydenhamhillproject.com
Best Wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact:
Andrew Neary 07436 049 480
Hannah Morgan 07769 306 933
Dion King 07901 737 269
Laury Jancauskas 07502 600 834
Security 07759 833 036