Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Tuesday 27 May 2025 in connection with the Sydenham Hill Estate Redevelopment Project.
Tuesday 27 – Friday 30 May; Saturday 31 May (08.00 – 13.00)
(Site closed on Bank Holiday Monday 26 May)
Block A
Cleaning & inspection of ground and first floor apartments
Finishing to 3rd floor apartments – lino, mastic and builders clean & protection removal
Snagging & finals to all apartments ongoing
Painting corridor ceilings
Lift commissioning continues
Paving to terraces
Block B
Sprinkler installation, 1st & 5th floor
Pre decoration snagging, 1st floor
Kitchens & tiling, 2nd floor
Electrical & mechanical 2nd fix
Doors & skirting, 5th floor
Plastering & mist coat 6th floor apartments
Corridor ceiling grids
Curtain walling delivery
Scaffold strike to perimeter
Hoist removal, Wednesday 28 May
Block C
Durasteel installation to plant room
Corridor ceiling boarding, lower ground floor
Pre-decoration snagging, first floor
Tiling to bathrooms & kitchens
Kitchen installations, various apartments
Electrical 2nd fix, 3rd floor
Final decorations to various apartments
Otto Close
Scaffold strike, top lift, drylining - houses 1-4
Zinc dormas, roof tiling, internal drylining - houses 5-7
Zinc dormas, roof tiling – houses 8-11
Pitch
Relocation of monitor (dust, noise & vibration) – Tuesday 27 May
Demolition works begin (from Tuesday, no works to pitch on Saturday)
If you have any queries, please contact us on info@sydenhamhillproject.com
Best Wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00