Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 2 June 2025 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 2 - Friday 6 June; Saturday 7 June (08.00 – 13.00)
Bean Tree Court, Block A
Snagging & finishing to all apartments ongoing, followed by cleaning & inspection
Lift commissioning continues
Paving to terraces
Landscaping to perimeter
Block B
Preparation of generator room for plant delivery
Pre-decoration snagging, 1st & 2nd floor
Kitchens & tiling, 3rd floor
Plastering 4th & 5th floor apartments
Doors & skirting, 6th floor
Curtain walling installation to atrium
Scaffold strike to perimeter
Hoist removal now w/c 9 June
Block C
Durasteel installation to plant room
Corridor ceilings
Tiling to bathrooms & kitchens
Electrical 2nd fix various apartments
Final decorations to various apartments
Otto Close
Brickwork snagging & rear elevation roof - houses 1-4
Zinc dormas, roof tiling to complete - houses 5-7
Zinc dormas, roof tiling – houses 8-11
Pitch
Demolition works begin Monday 2 June: Saw cut for separation cut to roof slab followed by demolition of slab & columns
No works to pitch on Saturday
If you have any queries, please contact us on info@sydenhamhillproject.com
Best Wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact:
Andrew Neary 07436 049 480
Hannah Morgan 07769 306 933
Dion King 07901 737 269
Laury Jancauskas 07502 600 834
Security 07759 833 036