Sydenham Hill Estate Weekly Works Update: w/c Monday 28 April 2025

Dear Neighbour,

Please find below the activities that are scheduled to take place from the week commencing Monday 28 April 2025 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 28 April – Friday 2 May; Saturday 3 May (08.00 – 13.00)

*The site will be closed on the bank holiday, Monday 5 May

 Block A

  • Curtain walling to community room

  • Finishing to corridors & ceilings

  • Latex floor to 2nd floor apartments

  • Snagging & finals to all apartments

  • Roof cladding panels to form plant enclosure

Block B

  • Gable brickwork

  • Doors & skirting, 3rd floor

  • Plastering & mist coat 4th floor apartments

  • Wall & ceiling closures, 4th floor

  • Mechanical sign off, 5th floor

  • Pipework installation, 6th floor

  • Tiling to 7th floor roof

  • Roof cladding panels to form plant enclosure, 6th floor

  • Completing Air Source Heat Pump connections

Block C

  • Scaffold Strike to perimeter & window cleaning

  • Window sill installation

  • Final decorations to ground & 1st floor apartments

  • Tiling to bathrooms & kitchens

  • Kitchen installations, 3rd floor

  • Ceiling closures & plastering, 3rd floor

Otto Close

  • Screed ground floor, roof covering & tiling, zinc work to dormas, houses 1-7

  • Installing roof trusses & dormas, houses 8-11

Deliveries

  • There are no planned large deliveries next week. There will be a screed lorry in Otto Close on Saturday 3 May, but is not expected to block the road

Notes/Future works

  • Please note that works are scheduled to commence on the ball court area from the week commencing 12 May. This will involve the demolition and reconstruction of the space to create usable under croft car parking and a new play surface for residents. The works are expected to take approximately three months to complete.

  • During the demolition phase, elevated noise levels are expected. Lovell will be engaging directly with nearby residents to discuss potential impacts and the measures in place to minimise disruption. The footpath by the pitch may be closed during these works, but a temporary footpath will be provided so that access is available at all times.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best Wishes,

The Sydenham Hill Project Team

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

 For site emergencies, please contact:

Andrew Neary 07436 049 480

Hannah Morgan          07769 306 933

Dion King                     07901 737 269

Laury Jancauskas         07502 600 834

Security 07759 833 036